FERC Transmission Siting Bill Would Make Data Centers Pay
ENMG Analysis
The Bipartisan American Affordability and Jobs Act of 2026 would make two significant changes to U.S. electricity policy if enacted. It would expand the Federal Energy Regulatory Commission’s authority to site certain interstate transmission projects and require data centers and other computational loads of at least 20 megawatts to pay their full associated transmission and incremental costs.
The bill was introduced in the Senate on September 30 by Senators Martin Heinrich, Mike Lee, Shelley Moore Capito, and Sheldon Whitehouse, who are bipartisan leaders of the Senate Energy and Natural Resources and Environment and Public Works committees. As the Senate Energy and Natural Resources Committee announced, the legislation is intended to reform federal permitting, expand grid infrastructure, and address the cost effects of rapidly growing electricity demand.
The proposal is not enacted law. Its sponsors introduced and released the legislation on September 30, but the publicly available bill text does not yet include a bill number or completed committee-referral information. Committee consideration, possible amendments, passage by both chambers, and presidential approval would still be required for the proposal to become law.
What the bill would change at FERC
The bill’s transmission provisions would alter how federal backstop siting authority works.
Under current Section 216 of the Federal Power Act, FERC’s backstop authority operates in conjunction with Department of Energy designations of National Interest Electric Transmission Corridors. In general terms, DOE identifies areas where transmission limitations or congestion may be harming consumers, and FERC can exercise specified siting authority under defined circumstances, including certain situations involving state inaction or denial.
The proposed legislation would remove the requirement that a project first be located within a DOE-designated corridor before FERC can use the expanded authority contemplated by the bill. It would allow FERC to issue permits for qualifying interstate transmission facilities directly, subject to the bill’s standards and procedures. That does not mean FERC would receive unlimited control over every local distribution project or retail electricity decision. The bill text includes a savings provision stating that the legislation would not give FERC authority over retail electricity sales or local distribution.
The practical effect would be to create a more direct federal pathway for selected interstate projects. That could matter for lines that cross multiple states, connect distant generation to growing load centers, or address congestion that cannot be resolved through a single state proceeding.

Why transmission siting has become more urgent
The U.S. grid is managing a difficult mismatch between where electricity is generated and where demand is growing.
Wind and solar projects are often developed in regions with strong natural resources, while major demand centers are concentrated around cities, manufacturing corridors, ports, and increasingly large computing campuses. Natural gas, nuclear, hydroelectric power, coal, battery storage, and other resources also depend on transmission or distribution infrastructure when electricity must move beyond the point of generation.
At the same time, interconnection queues contain large volumes of proposed generation and storage awaiting studies, network upgrades, and commercial decisions. Congestion can prevent lower-cost resources from reaching customers and can increase dependence on local generation during periods of high demand.
The Department of Energy and FERC have also been examining faster pathways for large electricity users. ENMG previously reported on the DOE’s push for faster large-load interconnection at FERC, including efforts to improve study procedures, readiness requirements, and cost recovery for large loads.
New transmission is not the only response. Reconductoring, advanced conductors, grid-enhancing technologies, storage, flexible load, and better operational data may increase effective capacity on existing infrastructure. ENMG has also examined the DOE’s SPARK transmission upgrade program and the DOE’s cancellation of three Biden-era transmission corridors, developments that illustrate the continuing debate over federal authority, local control, and the pace of grid construction.
The right of first refusal dispute
The legislation would also prohibit federal rights of first refusal for transmission facilities selected in regional or interregional plans.
A right of first refusal is the ability of an incumbent utility or transmission owner to build a project selected through a regional planning process before outside developers can compete for the work. Supporters of these rights argue that incumbent utilities already understand local systems, have established relationships with regulators and landowners, and remain responsible for operating and maintaining the infrastructure. They contend that continuity can reduce reliability risks and simplify project execution.
Opponents argue that automatic preference can limit competition, increase project costs, and reduce incentives to complete projects quickly. Allowing independent developers to compete could bring alternative financing structures, construction expertise, or lower-cost proposals.
The tradeoff is not simply between utilities and private developers. A competitive process must still establish clear reliability standards, ownership responsibilities, cost controls, and accountability for delays. Removing a right of first refusal could increase competition, but it would not by itself guarantee faster construction or lower rates.
The bill’s approach would therefore place greater emphasis on regional planning and competitive project development. How FERC, regional transmission organizations, independent system operators, state regulators, and incumbent utilities would implement that framework would be important if the proposal advances.
What the 20 MW data center provision would do
The cost-allocation language is directed at a specific category of large load. It would apply to data centers and other computational loads of 20 megawatts or more, rather than to all data centers or all commercial customers.
For covered loads, the bill would require the owners and operators to pay the full associated transmission and incremental costs connected to serving the load. It would also prevent those costs from being recovered from other customers. As Utility Dive reported, the proposal includes provisions addressing exit charges and the allocation of incremental costs for computational loads at or above the 20 MW threshold.
That distinction matters. A 20 MW facility may require more than a simple service connection. Its demand could trigger substation work, transmission upgrades, network reinforcement, protection changes, and additional generation or capacity arrangements. The bill seeks to ensure that the customer driving those investments carries the associated financial responsibility.
The language does not state that every existing data center would immediately face a new charge. It addresses covered computational loads at or above the threshold within the bill’s proposed framework. Implementation details, including how costs would be identified and assigned, could become a major subject of committee debate and regulatory interpretation.

Benefits and limitations for the energy system
The proposed cost rule could protect residential customers, small businesses, and other ratepayers from subsidizing infrastructure built primarily for a large computational customer. It could also give utilities and developers clearer financial signals before construction begins.
For data center companies, full cost responsibility could increase project expenses and affect site selection. Locations with existing transmission capacity, nearby generation, or flexible operating arrangements could become more attractive. Some developers may respond by adding batteries, onsite generation, flexible computing schedules, or long-term power contracts.
ENMG has covered flexible interconnection for data center load, an approach in which large customers agree to operate within defined limits during constrained conditions. Flexible interconnection could help some facilities connect sooner, but it does not eliminate the need for new generation, transmission, fuel supply, or distribution equipment when demand continues to grow.
The provision could also influence the generation mix. Natural gas may provide firm power in regions with available pipeline capacity. Existing nuclear and hydroelectric plants may become more valuable to large customers seeking continuous electricity. Wind and solar can contribute energy, while batteries and flexible computing may help manage periods of variability. Manufacturing facilities, hydrogen projects, industrial electrification, and other large loads could face similar questions about who pays for network expansion, although the bill’s specific computational-load provisions do not automatically apply to every large industrial customer.
There are limitations as well. Assigning costs to data centers may protect other ratepayers, but it will not resolve permitting delays, equipment shortages, transformer constraints, or the availability of generation. A federal siting pathway may shorten one part of the process while leaving landowner negotiations, environmental review, Tribal consultation, state requirements, and judicial challenges in place.
What to watch next
The immediate issue is whether the Senate Energy and Natural Resources Committee schedules hearings or markup and whether lawmakers revise the transmission and computational-load language.
Key questions include:
- How would FERC determine which interstate projects qualify for the expanded siting authority?
- What environmental, Tribal, state, and local review requirements would remain?
- How would regional planners structure competition after federal rights of first refusal are prohibited?
- How would utilities calculate the full associated and incremental costs of a 20 MW or larger computational load?
- Would the rules apply to new facilities, expansions, or changes in service arrangements?
- How would the bill interact with existing FERC large-load proceedings and state cost-allocation rules?
- Can Congress reach agreement on a proposal that expands federal authority while protecting ratepayers and local interests?
The bill responds to real grid-planning pressures: rising electricity demand, congested transmission paths, long interconnection queues, and the concentration of new computing load in particular regions. Its proposed solution combines stronger federal siting authority, more competition among transmission developers, and greater cost responsibility for large data centers.
Whether that combination can attract enough support to become law remains uncertain. For now, the legislation is best understood as an opening framework for debate rather than a change in current law.
Keep In Touch with Shale Magazine
As the new era of energy unfolds, you can bet we’ll be the boots on the ground to keep you informed. Subscribe to Shale Magazine for sharp insight into the arenas that matter most to your life. And don’t forget to listen to our riveting podcast, The Energy Mixx Radio Show, where our very own Kym Bolado interviews the most extraordinary thought leaders, business innovators, and industry experts of our time.